Project: Groundworks for new stables
- Construct 90m of new access road
- 150m of water pipe/electric ducts
- Construct concrete base with brickwork to accept new stables
- 70m2 of block paving for courtyard
|
|
|
|
|
Project: 40m x 40m menage
- Divert existing .225mm drain and form new outfall
- 600m3 cut and fill to formation level
- Install membrane and land drains
- Install membrane and size stone
- Level silica sand and wood fibre surface
- Erect fencing and landscaping
|
|
|
|
|
Project: Flood prevention works at The Wrekin, Shropshire
- Install 75m.300mm of pipe
- Repair and reprofile paths to minimise water erosion
|
|
|
|
|
Project: Re-establish access at The Wrekin
- Removal of flytipped soil
- Repair and re-profile track
- Install gate
|
|
|
|
|
Project: Access road into woods
- Reduce dig 1400m2 to formation levels
- Grade 250m3 of recycled stone
- Install gate
|
|
|
|
|
Andrew Donald Groundworks, 33 Pemberton Road, Admaston, Telford, Shropshire, TF5 0BB, UK